Project Description
The Mid-County Library was heavily damaged from Hurricane Ian. Establish the requirements to repair the facility through standard critical path processes. Design and repair the facility to its pre-storm condition taking the opportunity to make improvements where applicable.Project Location
Mid-County Regional Library
2050 Forrest Nelson Blvd.
Port Charlotte, Florida 33952
Project Impacts
Lead times for equipment
Insurance review timelines
Latest Updates
Pre-Design meeting held 1/16/2024
Scheduling stakeholder kick-off meeting beginning of March 2024
Budget
Phase | Cost |
---|---|
Design | $678,177.00 |
Construction | $3,869,224.45 |
Total Budget | $4,547,401.45 |
Hurricane Fund
Insurance Reimbursements
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/16/2024 | 10/25/2024 | |
Construction | 10/28/2024 | 10/31/2025 | |
Turnover & Closeout | 11/03/2025 | 01/02/2026 |
Project Phase
Planning and Project Approval
Last Updated
03/07/2024
Project Manager
Vicki Chichura
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
CSA
Construction Contractor
Wharton Smith